
What Goes Into an ADU Foundation in Los Angeles?
Short answer. Most backyard ADUs in Los Angeles sit on a slab on grade. The city's prescriptive minimums call for footings at least 24 inches deep at the exterior walls, a slab at least 3 1/2 inches thick with 1/2 inch rebar at 16 inches each way, a vapor barrier under it, and anchor bolts cast into the edges. Your engineer's stamped plans govern the real job.

An ADU, short for accessory dwelling unit, is a small building with every requirement of a house, and the foundation is the first part that gets inspected. We build ADU foundations from the engineer's stamped plans. We do not design them. This article explains what is on those plans, so the numbers on the sheet and the work in the trench make sense when you see them.
Slab on grade or raised foundation?
A slab on grade is the usual choice on a flat backyard. A raised foundation suits a sloping lot or an owner who wants a crawl space. Your designer picks, and the lot usually decides.
| Slab on grade | Raised foundation | |
|---|---|---|
| What it is | One pour. The floor and the footings are the same concrete, thickened under the walls | Continuous footings and short concrete stem walls, with a framed wood floor above a crawl space |
| Best fit | Flat or nearly flat pads | Sloping ground, where footings step down in level sections |
| Plumbing | Drain and water lines go in the ground before the pour and are sealed in | Lines hang under the floor and stay reachable |
| Moisture control | Vapor barrier under the slab | Crawl space ventilation and clearance, per the plans |
| Floor height | A step above the yard | Higher, with steps or a landing at the door |
| Concrete work | Trenches, base, barrier, steel, then one large pour | Footings and stem walls, often poured in two stages |
What do the engineer's plans specify?
Everything we build to: footing width and depth, slab thickness, bar size and spacing, concrete strength, and where each bolt goes. The Los Angeles Department of Building and Safety (LADBS) publishes prescriptive minimums for one story wood frame houses, and they show the starting point an ADU's plans are measured against.
- Soil. LADBS considers all soil in the City of Los Angeles expansive unless an approved soils report proves otherwise. Expansive soil swells when wet and shrinks when dry, and the footing rules below exist to deal with that.
- Footings. At least 24 inches below natural and finished grade at exterior walls and 18 inches at interior bearing walls, continuous under those walls.
- Footing steel. Four 1/2 inch bars, two near the bottom and two near the top, with 3 inches of concrete cover where the concrete is cast against earth.
- Slab. At least 3 1/2 inches thick, with 1/2 inch bars no more than 16 inches apart each way.
- Concrete. A minimum strength of 2,500 psi.
Those numbers come from LADBS bulletins P/BC 2020-004 and P/BC 2017-116. The first one says of itself that it is no substitute for accurate drawings prepared for the project. Engineered plans often call for more: wider footings, heavier bar, pads under posts, a higher concrete strength. If a soils report was done, its recommendations are on the plans too.
LADBS also runs a Standard Plan Program of ADU designs it has approved in advance. Even with one of those, the department reviews the plan against your property for zoning and foundation needs, so the foundation is never fully off the shelf.
What goes under and into the slab?
In order, from the dirt up:
- Underslab plumbing. Drain, waste and water lines are trenched in and stubbed up where the bathroom and kitchen walls will stand. Electrical conduit that runs under the slab goes in now too. Another trade usually does this work, and it has to be finished before ours covers it.
- Base. The LADBS prescriptive slab sits on 4 inches of coarse aggregate, or on 2 inches of sand over a moisture barrier. California's green building code, CALGreen, calls for a capillary break under slab foundations: a 4 inch base of clean aggregate, 1/2 inch or larger, with a vapor retarder in direct contact with the concrete.
- Vapor barrier. Heavy plastic sheeting that keeps ground moisture from rising through the slab into the flooring. The LADBS prescriptive sheet lists 6 mil as its minimum. Seams are lapped and the sheeting is sealed around pipes as the plans and the product call for.
- Rebar. Bars are tied on a grid and propped on small concrete blocks so the steel ends up inside the slab, not under it.
- Anchor bolts and hold-downs. Anchor bolts tie the wall's bottom plate to the concrete. The LADBS prescriptive sheet uses 1/2 inch by 10 inch bolts embedded 7 inches, no more than 6 feet apart, with at least two per piece of plate. Hold-downs are heavier anchors at the ends of shear walls, the wall panels that resist earthquake forces, and the plans give each one's location.
Bolts and hold-downs get set before the pour, tied in place to the plan dimensions. A hold-down that lands a few inches off its post cannot be moved after the concrete hardens, and the fix is an engineer's letter and epoxy anchors. That is why placement gets checked against the plans before the pour.
What gets inspected before the pour?
The trenches, the steel and the hardware, before any concrete is ordered. On a permitted job the inspector has to see the work that is about to be buried, and nothing gets covered until it is signed off. In practice that means the footing trenches are open and clean, the forms are set, the rebar is tied and supported, and the bolts and hold-downs are hung in place.
Underslab plumbing is inspected on its own before the base and barrier go over it. The exact inspections, and their order, are listed on your permit. We order the pump and the ready mix trucks once the approvals are in.
What changes on a hillside lot?
The foundation gets deeper and the paperwork gets longer. Footings on a slope step down in level sections, and engineers often tie them together with grade beams, which are reinforced concrete beams cast in the ground. A soils report is far more likely to be required, and the cut and fill for the pad can need a grading permit of its own.
Water matters more on a slope as well. The LADBS expansive soil bulletin wants drainage next to the footings carried away from the structure by an apron at least 3 feet wide, sloped at 2 percent or more, to an approved device that will not erode. If the pad needs a retaining wall or yard drains, we build those too.
This article describes the City of Los Angeles. Santa Clarita, Burbank, Glendale and the unincorporated county run their own building departments, and California's housing department, HCD, publishes a statewide ADU Handbook, updated in March 2026. Confirm the rules for your address with your own building department.
Ikon Concrete Design builds concrete foundations for ADUs, additions and garages across Los Angeles north of downtown and the Santa Clarita Valley. Send the plans through the contact page or call (818) 464-5763 for a free estimate.
More questions
Whatever the stamped plans say. The Los Angeles prescriptive minimum for a one story wood frame building is 3 1/2 inches with 1/2 inch rebar at 16 inches each way, and engineered slabs are often thicker. The edges under the walls are footings, which the same prescriptive rules put at least 24 inches deep at exterior walls.
Not always. LADBS treats all soil in the city as expansive unless an approved soils report proves otherwise, and its expansive soil bulletin lets new construction either submit a soils report or build the footings to its prescriptive rules. The inspector can still require a report based on site conditions, and hillside lots usually need one.
Sometimes, and that is your engineer's and the plan checker's call. An old garage slab may have no vapor barrier, shallow footings and no bolts where new walls need them. Plans for conversions often add new footings or dowel new concrete into the old with epoxied steel.
A plumber, not the concrete crew. The lines go in after the pad is graded and before the base, vapor barrier and rebar. Tell us who your plumber is at the estimate so the two schedules line up.
Related services
Written by the Ikon Concrete Design team in Sylmar, California. Ikon Concrete Design is a family owned concrete contractor run by Gilbert Rico since 1999, California license770901. This article is general information. Codes, fees and prices change, so check with your building department and get an on-site estimate before you plan around a number.

Concrete contractor in Santa Clarita and the San Fernando Valley
Family OwnedSince 1999
California contractor license 770901. C-8 Concrete and B General Building. Free estimates.
Get Your Concrete Poured In Three Easy Steps
Send A Message
Call, text or send the form with a few details, and photos if you have them. We reply the day we get it.
Step 1Free Estimate
We walk the site with you, measure, talk through finishes and drainage, and give you a price. No charge.
Step 2We Build It
Most jobs start about two weeks after you approve the estimate. We demo, form, pour, finish and haul off the mess.
Step 3

Ready For Your Concrete Project?
Family owned since 1999. California license 770901. Free estimates.
